| Lexington Area MPO FY 2008 Federal Funding Obligations (October 1 2007 thru September 30 2008) | ||||||||||||||||||||
| County | Form | Phase | File Number | Item Number | Project Number | FUND CODE | APPN CODE | Federal $ Amount | Date Processed | Approved in FMIS | WEEK PROCESSED | Toll Credit Amount | TYPE WORK | DESCRIPTION | PREFIX | ROUTENO | SUFFIX | BMP | EMP | LENGTH |
| Fayette | AC conv | D | 471 | 7-279 | NH 2682(9) | BRO | Q100 | $270,162.92 | 07/31/2008 | 08/11/2008 | 08/01/2008 | $54,032.58 | I-CHANGE RECONST(O) | PRELIMINARY DESIGN FUNDS FOR RECONSTRUCTION OF KY-4/US-60 (VERSAILLES ROAD) INTERCHANGE. | KY | 4 | 4.335 | 4.951 | ||
| Fayette | M | D | 136 | 7-593 | CM 3003(129) | CM | Q400 | $13,921.60 | 01/09/2008 | 01/25/2008 | 01/11/2008 | NEW ROUTE(O) | NEWTOWN PIKE EXTENSION FROM WEST MAIN ST. TO SOUTH LIMESTONE ST. IN LEXINGTON. (98KYDN)(2005HPP-KY114)(SEE 7-593.02 FOR ADDITIONAL "HPP" FUNDING) | |||||||
| Fayette | AC conv | C | 289 | 99-219.06 | CM 3003(219) | CM | H400 | $1,000,000.00 | 05/09/2008 | 05/22/2008 | 05/09/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS | |||||||
| Fayette | AC conv | C | 274 | 99-219.05 | CM 08571(1) | CM | Q400 | $153,000.00 | 05/09/2008 | 05/22/2008 | 05/09/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS. (2004BOPP)(2006BOPP) | |||||||
| Fayette | AC conv | C | 289 | 99-219.06 | CM 3003(219) | CM | Q400 | $1,000,000.00 | 05/09/2008 | 05/22/2008 | 05/09/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS | |||||||
| Fayette | PR-1 | nonhwy | 296 | 99-219.06 | CM 3003(220) | CM | L400 | $320,000.00 | 05/14/2008 | 05/27/2008 | 05/16/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS | |||||||
| Fayette | PR-1 | nonhwy | 198 | 99-219.05 | CM 3003(180) | CM | H400 | $319,900.00 | 05/20/2008 | 05/29/2008 | 05/23/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS. (2004BOPP)(2006BOPP) | |||||||
| Fayette | AC conv | nonhwy | 228 | 99-219.06 | CM 3003(195) | CM | H400 | $145,000.00 | 05/28/2008 | 06/09/2008 | 05/30/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS | |||||||
| Fayette | AC conv | nonhwy | 280 | 99-219.06 | CM 3003(216) | CM | Q400 | $88,000.00 | 05/09/2008 | 06/11/2008 | 05/09/2008 | CONGESTION MITIGTN(O) | NON-ATTAINMENT AREAS STATEWIDE CMAQ FUNDED PROJECTS | |||||||
| Fayette | M | D | 471 | 7-279 | NH 2682(9) | F | 0100 | $270,162.92 | 08/14/2008 | 08/22/2008 | 08/15/2008 | $54,032.58 | I-CHANGE RECONST(O) | PRELIMINARY DESIGN FUNDS FOR RECONSTRUCTION OF KY-4/US-60 (VERSAILLES ROAD) INTERCHANGE. | KY | 4 | 4.335 | 4.951 | ||
| Fayette | M | C | 1 | no# | HIAA 4(8) | HIAA | 4210 | $189,900.00 | 04/10/2008 | 04/10/2008 | 04/11/2008 | I-75 at Lexington. | ||||||||
| Fayette | PR-1 | RW | 44 | 7-593.10 | HPP 0114(1) | HPP | HY10 | $2,737,512.00 | 04/09/2008 | 04/23/2008 | 04/11/2008 | $547,502.40 | ||||||||
| Fayette | PR-1 | RW | 44 | 7-593.10 | HPP 0114(1) | HPP | LY10 | $1,257,488.00 | 04/09/2008 | 04/23/2008 | 04/11/2008 | $251,497.60 | ||||||||
| Fayette | PR-1 | RW | 45 | 7-593.40 | HPP 0114(2) | HPP | LY10 | $6,106,300.00 | 04/09/2008 | 04/23/2008 | 04/11/2008 | $1,221,260.00 | ||||||||
| Fayette | partial AC conv | C | 2040 | 7-2016.50 | IM 0754(61) | IM | L010 | $6,000,000.00 | 04/22/2008 | 04/28/2008 | 04/25/2008 | $600,000.00 | ||||||||
| Fayette | AC conv | C | 2040 | 7-2016.50 | IM 0754(61) | IM | L010 | $4,141,196.74 | 08/15/2008 | 09/02/2008 | 08/15/2008 | $414,119.67 | ||||||||
| Fayette | partial AC conv | C | 426 | 7-366.10 | NH 2682(5) | NH | L050 | $3,000,000.00 | 04/21/2008 | 04/23/2008 | 04/25/2008 | $600,000.00 | ||||||||
| Fayette | partial AC conv | C | 426 | 7-366.10 | NH 2682(5) | NH | L050 | $613,488.43 | 07/02/2008 | 07/02/2008 | 07/04/2008 | $122,697.67 | ||||||||
| Fayette | AC conv | C | 426 | 7-366.10 | NH 2682(5) | NH | L050 | $3,134,884.34 | 07/07/2008 | 07/14/2008 | 07/11/2008 | $626,976.89 | ||||||||
| Fayette | AC conv | D | 471 | 7-279 | NH 2682(9) | NH | L050 | $229,837.08 | 07/31/2008 | 08/11/2008 | 08/01/2008 | $45,967.42 | I-CHANGE RECONST(O) | PRELIMINARY DESIGN FUNDS FOR RECONSTRUCTION OF KY-4/US-60 (VERSAILLES ROAD) INTERCHANGE. | KY | 4 | 4.335 | 4.951 | ||
| Fayette | AC conv | C | 2040 | 7-2016.5 | NH 754(61) | NH | L050 | $4,920,169.02 | 08/15/2008 | 09/02/2008 | 08/15/2008 | $492,016.90 | PAVEMENT REHAB-INT(P) | I-75 SB PAVEMENT REHAB: MILL 4" AND OVERLAY FROM MP 111.82 TO MP 117.452 AND 1.5" OVERLAY FROM MP 107.426 TO MP 110.264 AND MP 117.452 TO MP 117.967 INCLUDING I-CHNG RAMPS AND LANE ADDITION FROM MP 115.226 TO MP 117.000. (2006BOPC) | I | 75 | 107.426 | 110.264 | 9 | |
| Fayette | PR-1 | nonhwy | 115 | no# | PL 0009(5) | PL | L450 | $301,655.00 | 05/20/2008 | 06/10/2008 | 05/23/2008 | Lexington-Fayette Urbanized Area. | ||||||||
| Fayette | M | U | 228 | 7-127 | STP 4181(13) | STP | Q770 | $35,000.00 | 10/10/2007 | 10/23/2007 | 10/12/2007 | $7,000.00 | I-CHANGE RECONST(O) | NEW CIRCLE ROAD RECONSTRUCTION OF WINCHESTER I-CHANGE | KY | 4 | 12.28 | 13.13 | 0.8 | |
| Fayette | M | D | 29 | 7-590 | STPM 0035(1) | STPM | LEX L230 | $50,775.00 | 02/14/2008 | 02/21/2008 | 02/15/2008 | $10,155.00 | RECONSTRUCTION(O) | LIBERTY ROAD/TODDS ROAD CADENTOWN BYPASS: RECONSTRUCT FROM 0.2 MI S OF ANDOVER FOREST DRIVE/FOREST HILL DRIVE TO 0.1 MI S OF GRAFTONS MILL LANE.(98KYDN)(SEE 7-225.00 FOR SECTION 2)(2006BOPP) | KY | 1927 | 1 | 2.45 | 1.5 | |
| Fayette | M | nonhwy | 2237 | 7-996.08 | STPM 3003(185) | STPM | LEX 33C0 | $127,900.00 | 03/18/2008 | 04/07/2008 | 03/21/2008 | MATCHED FED FUNDS(O) | DEDICATED FEDERAL-AID STP FUNDS EARMARKED FOR LEXINGTON URBANIZED AREA AND SUBJECT TO MPO CONTROL. (2002BOPP) | |||||||
| Fayette | M | D | 1267 | 7-223 | STPM 8530(1) | STPM | LEX L230 | $200,000.00 | 05/16/2008 | 05/28/2008 | 05/16/2008 | $40,000.00 | MAJOR WIDENING(O) | LEESTOWN ROAD; WIDEN TO 4 LANES FROM EXISTING 4-LANE NEAR NEW CIRCLE ROAD TO MASTERSON PARK (LFUCG T.I.P.). (SEE 7-223.02 FOR "SLX" COMPONENT) | US | 421 | 2.296 | 3.842 | 1.5 | |
| Fayette | M | D | 1384 | 7-231 | STPM 3003(121) | STPM | LEX Q230 | $8,000.00 | 05/16/2008 | 05/28/2008 | 05/16/2008 | MATCHED FED FUNDS(O) | ADD BIKE LANE ON ROSE STREET FROM ROSE LANE TO EUCLID. (LFUCG T.I.P.) (LOCAL MATCH)(ALL WORK BY LFUCG) | CS | 3817 | 0.504 | 0.591 | |||
| Fayette | M | nonhwy | 2573 | 7-227.07 | STPM 3003(222) | STPM | LEX 33C0 | $54,000.00 | 05/21/2008 | 05/29/2008 | 05/23/2008 | MATCHED FED FUNDS(O) | VARIOUS 'SLX' CONTINUING PROGRAM PROJECTS (RIDESHARE/MOBILITY, AIR QUALITY PLANNING, TRAFFIC SIGNAL) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | |||||||
| Fayette | PR-1 | nonhwy | 2572 | 7-227.07 | STPM 3003(221) | STPM | LEX H230 | $102,000.00 | 05/21/2008 | 05/29/2008 | 05/23/2008 | MATCHED FED FUNDS(O) | VARIOUS 'SLX' CONTINUING PROGRAM PROJECTS (RIDESHARE/MOBILITY, AIR QUALITY PLANNING, TRAFFIC SIGNAL) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | |||||||
| Fayette | PR-1 | nonhwy | 2574 | 7-227.07 | STPM 3003(223) | STPM | LEX H230 | $134,000.00 | 05/21/2008 | 05/29/2008 | 05/23/2008 | MATCHED FED FUNDS(O) | VARIOUS 'SLX' CONTINUING PROGRAM PROJECTS (RIDESHARE/MOBILITY, AIR QUALITY PLANNING, TRAFFIC SIGNAL) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | |||||||
| Fayette | PR-1 | nonhwy | 2575 | 7-227.07 | STPM 3003(224) | STPM | LEX H230 | $190,000.00 | 05/21/2008 | 05/29/2008 | 05/23/2008 | MATCHED FED FUNDS(O) | VARIOUS 'SLX' CONTINUING PROGRAM PROJECTS (RIDESHARE/MOBILITY, AIR QUALITY PLANNING, TRAFFIC SIGNAL) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | |||||||
| Fayette | AC Conv | RW | 2367 | 7-223 | STPM 8530(2) | STPM | LEX L230 | $3,000,000.00 | 06/06/2008 | 07/02/2008 | 06/06/2008 | MAJOR WIDENING(O) | LEESTOWN ROAD; WIDEN TO 4 LANES FROM EXISTING 4-LANE NEAR NEW CIRCLE ROAD TO MASTERSON PARK (LFUCG T.I.P.). (SEE 7-223.02 FOR "SLX" COMPONENT) | US | 421 | 2.296 | 3.842 | 1.5 | ||
| Fayette | AC Conv | U | 2373 | 7-223 | STPM 8530(3) | STPM | LEX L230 | $4,800,000.00 | 06/06/2008 | 07/02/2008 | 06/06/2008 | $960,000.00 | MAJOR WIDENING(O) | LEESTOWN ROAD; WIDEN TO 4 LANES FROM EXISTING 4-LANE NEAR NEW CIRCLE ROAD TO MASTERSON PARK (LFUCG T.I.P.). (SEE 7-223.02 FOR "SLX" COMPONENT) | US | 421 | 2.296 | 3.842 | 1.5 | |
| Fayette | M | D | 1392 | 7-226 | STPM 8532(5) | STPM | LEX Q230 | $280,000.00 | 07/02/2008 | 07/16/2008 | 07/04/2008 | NEW ROUTE(O) | CITATION BOULEVARD - PHASE II; FROM SOUTHERN RR TO LEESTOWN ROAD (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | |||||||
| Fayette | PR-1 | U | 2587 | 7-224.5 | STPM 8552(7) | STPM | LEX 33C0 | $10,000.00 | 07/10/2008 | 07/22/2008 | 07/11/2008 | $2,000.00 | MINOR WIDENING(O) | CLAYS MILL ROAD; WIDEN FROM NEW CIRCLE ROAD TO TWAIN RIDGE DRIVE (SECTION 2) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG)(2004BOPP) | CS | 4174 | 2.01 | 3.883 | 1.8 | |
| Fayette | M | C | 144 | 7-590.10 | DPR 0035(4) | STPM | LEX H230 | $4,998,558.00 | 07/08/2008 | 07/22/2008 | 07/11/2008 | $99,711.00 | ||||||||
| Fayette | PR-1 | U | 2587 | 7-224.5 | STPM 8552(7) | STPM | LEX H230 | $760,000.00 | 07/10/2008 | 07/22/2008 | 07/11/2008 | MINOR WIDENING(O) | CLAYS MILL ROAD; WIDEN FROM NEW CIRCLE ROAD TO TWAIN RIDGE DRIVE (SECTION 2) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG)(2004BOPP) | CS | 4174 | 2.01 | 3.883 | 1.8 | ||
| Fayette | PR-1 | RW | 2340 | 7-220 | STPM 3003(189) | STPM | LEX H230 | $150,000.00 | 07/14/2008 | 07/23/2008 | 07/18/2008 | $4,000.00 | BIKE/PED FACIL(O) | RICHMOND ROAD MULTIUSE PATH IN LEXINGTON BETWEEN EAGLE CREEK DRIVE AND JACOBSON PARK. (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | US | 25 | 8.4 | 9.55 | 1 | |
| Fayette | AC Conv | RW | 2424 | 7-224.5 | STPM 8552(5) | STPM | LEX L230 | $403,000.00 | 07/31/2008 | 08/13/2008 | 08/01/2008 | $80,600.00 | MINOR WIDENING(O) | CLAYS MILL ROAD; WIDEN FROM NEW CIRCLE ROAD TO TWAIN RIDGE DRIVE (SECTION 2) (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG)(2004BOPP) | CS | 4174 | 2.01 | 3.883 | 1.8 | |
| Fayette | M | D | 1392 | 7-226 | STPM 8532(5) | STPM | LEX L230 | $35,154.00 | 08/28/2008 | 09/16/2008 | 08/29/2008 | $7,030.80 | NEW ROUTE(O) | CITATION BOULEVARD - PHASE II; FROM SOUTHERN RR TO LEESTOWN ROAD (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | ||||||
| Fayette | M | D | 1392 | 7-226 | STPM 8532(5) | STPM | LEX Q230 | $733,846.00 | 08/28/2008 | 09/16/2008 | 08/29/2008 | NEW ROUTE(O) | CITATION BOULEVARD - PHASE II; FROM SOUTHERN RR TO LEESTOWN ROAD (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | |||||||
| Fayette | M | C | 2334 | 7-218 | STPM 8594(5) | STPR | L240 | $499,900.00 | 11/29/2007 | 12/06/2007 | 11/30/2007 | MINOR WIDENING(O) | LOUDON AVENUE IN LEXINGTON; WIDEN TO 3-LANES FROM OAKHILL DRIVE TO WINCHESTER ROAD. (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | CS | 2230 | 0.558 | 1.401 | 0.89 | ||
| Fayette | M | C | 2334 | 7-218 | STPM 8594(5) | STPR | Q240 | $229,500.00 | 11/29/2007 | 12/06/2007 | 11/30/2007 | $45,900.00 | MINOR WIDENING(O) | LOUDON AVENUE IN LEXINGTON; WIDEN TO 3-LANES FROM OAKHILL DRIVE TO WINCHESTER ROAD. (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | CS | 2230 | 0.558 | 1.401 | 0.89 | |
| Fayette | AC conv | C | 2334 | 7-218 | STPM 8594(5) | STPR | L240 | $3,171,568.90 | 06/03/2008 | 07/22/2008 | 06/06/2008 | MINOR WIDENING(O) | LOUDON AVENUE IN LEXINGTON; WIDEN TO 3-LANES FROM OAKHILL DRIVE TO WINCHESTER ROAD. (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | CS | 2230 | 0.558 | 1.401 | 0.89 | ||
| Fayette | M | C | 2334 | 7-218 | STPM 8594(5) | STPR | L240 | $483,351.10 | 06/03/2008 | 07/22/2008 | 06/06/2008 | MINOR WIDENING(O) | LOUDON AVENUE IN LEXINGTON; WIDEN TO 3-LANES FROM OAKHILL DRIVE TO WINCHESTER ROAD. (LFUCG T.I.P.) (LOCAL MATCH) (ALL WORK BY LFUCG) | CS | 2230 | 0.558 | 1.401 | 0.89 | ||
| Fayette | M | D | 1523 | 7-912 | STPS 8531(9) | STPS | Q210 | $20,000.00 | 01/28/2008 | 02/04/2008 | 02/01/2008 | $4,000.00 | SAFETY-HAZARD ELIM(P) | INTERSECTION OF KY1681 & ALEXANDRIA DRIVE AT WUB OF LEXINGTON; CONSTRUCT A ROUNDABOUT (2000BOP)(04CCR) | KY | 1681 | 4.5 | 4.7 | 0.2 | |
| Lexington Area MPO Zvarious Project | M | C | 391 | 7-35 | HIAA 3003(187) | HIAA | 4210 | $210,000.00 | 03/05/2008 | 04/08/2008 | 03/07/2008 | ITS(P) | INSTALLATION OF AN INITIAL "ADVANCE TRANSPORTATION MANAGEMENT SYSTEM" FOR THE I-64/75 COMBINED ROUTE IN THE BLUEGRASS REGION. (2004BOPC) | |||||||
| Jessamine | partial AC conv | C | 33 | 4-125.10 | HPP 0111(3) | HPP | LY10 | $221,883.00 | 02/22/2008 | 03/04/2008 | 02/22/2008 | $44,376.60 | ||||||||
| Jessamine | partial AC conv | D | 9 | 7-249 | HPP 0160(2) | HPP | LY20 | $184,574.00 | 02/22/2008 | 03/26/2008 | 02/22/2008 | $36,914.80 | FEASIBILITY STUDY(O) | FEASIBILITY STUDY OF CONSTRUCTION ON U.S. 27 TO I-75 CONNECTOR ROAD, JESSAMINE COUNTY. (2005HPP-KY160) | ||||||
| Zvarious | M | C | 391 | 7-35 | HIAA 3003(187) | HIAA | 4210 | $210,000.00 | 03/05/2008 | 04/08/2008 | 03/07/2008 | ITS(P) | INSTALLATION OF AN INITIAL "ADVANCE TRANSPORTATION MANAGEMENT SYSTEM" FOR THE I-64/75 COMBINED ROUTE IN THE BLUEGRASS REGION. (2004BOPC) | |||||||